CB02b then CB02a as they need those two fitted in place and secured for the sponsons and UB01 units to the fitted correctly, they also need to clear that space at the front end of the dock to locate the Gas turbines once the lower half of the fwd stbd sponson has been fitted.
On thing that looks apparent is there are still no signs of fittings in the fwd deck lift edges to indicate a deck lift could be fitted anytime soon. the two white tents may indicate they are installing the runners either side of the hanger opening, but they need the gear on the sponson edges as well.
(See i said they were on holiday, thus the gap in updates

)